Turnkey Construction

Let's Build Green-er Building

Low Life cycle cost. Healthier Buildings.

Free online Consulation

    Free Online Consultation

  • Connect via Video call with our Expert and describe your requirement, look and feel of your project.

    Our Quote

  • We estimate the cost of your project based on your requirement and our past experiences and prevalent market prices.

  • We give you quote of our fees based on Cost of Project.

Strike a deal

    Strike a Deal

  • Signing of Contract describing Deliverable, Time Schedule and Payment Stages clearly.

  • For sample contract, please visit:

1% Payment

Finalise design _ Statutory approval

    Finalize Design and Statutory Approval

    (30-45 Days)
  • Finalize design of your project as per your taste and requirement.

  • After you finalize, we will go ahead and get statutory approval for the design from the concerned Authority.

2.5% Payment

Handover Site

    Handover Site (Dismantling if required)

    (30-45 Days)
  • We start dismantling existing structure after getting NOC from RWA and local authority.

  • Preparation of Good for Construction drawings.

  • In case of no dismantling, this stage coincides with Stage 6.

2.5% Payment

Foundation

    Foundation

    (20 Days)
  • We lay strong foundation in consultation with our Structural Engineer supervised by our Project Manager.

  • Day to day monitoring by our Civil Engineer to ensure Quality construction.

4% Payment

start of each slab

    Start of Slab Work

    (60-180 Days)
  • Starting of laying Structural members: Column, Beam and Slabs.

  • Brickwork and Services work will start simultaneously to speed up construction.

50% Payment divided equally among total number of Slabs

flooring

    Flooring

    (240 Days)
  • We place order for flooring material as per your taste.

  • Flooring work begins!

15% Payment on placement of order

Woodwork and painting

    Woodwork and Painting

    (285 Days)
  • Starting Woodwork and painting after the flooring is complete.

  • Placing order/Making custom doors and windows.

  • Placing order for Paints/Wallpapers as per design finalized.

15% Payment on Placement of order

Interior Installations

    Interior Installation

    (315 Days)
  • Placing order for Interior finishes like Sink, Fans, Lights as per your requirement.

  • Starting installation of W/C, Sink, Modular Kitchen as per requirement.

8% Payment on Placement of order

Completion certificate _ handover

    Completion

    (330 Days)
  • Handing over Completion certificates, Warranty certificates.

  • Handing over Electrical, Plumbing drawings for future references.

  • Cake cutting!

  • Completion Certificate.

2% Payment on Handover of Project

SOP for Turnkey Construction with Payment Stages and Tentative Schedule.

Package Name: Qi Homes

S.No. Stages Payment(in %age of cost of construction) Time Stage Description
1 Tell us your requirement (3 floors, 6 bedrooms, etc.)
    Free
    -
    You reach out to us.
2 We tell you exact cost of construction.
    Free
    -
    Our quote.
3 Strike a deal
    1%
    -
    Signing of Escalation free Turnkey Contract. We connect you to our Architect.
4 Finalize Design & Statutory Approval
    2.5%
    30-45 Days
    Finalize design with our Architect and we go ahead with Statutory Approvals.
5 Handover Plot (Dismantling)
    2.5%
    Day O
    Dismantling begins after Approval. In case no dismantling, this stage coincides with Stage 6
6 Foundation
    4%
    Day 20
    We lay strong foundation for your building in consultation with our Structural Engineer.
7 Start of Each Slab (Brickwork & Services will start simultaneously)
    50% (Divided equally over total number of Slabs)
    60-180 days
    Starting of laying Structural members: Column, Beam and Slabs. Brickwork and Services work will start simultaneously to speed up construction.
8 Flooring
    15%
    Day 240
    On placement of order for Flooring material.
9 Woodwork and Painting
    15%
    Day 285
    On placement of order for Paint and Woodwork material.
10 Interior Installations (W/C, Lights, Fans, etc)
    8%
    Day 315
    On Placement of order of required fixtures.
11 Completion Certificate & Handover
    2%
    Day 330
    On Handover of your building.